Probabilistik Durasi Proyek Konstruksi Menggunakan Integrasi Critical Path Method dan Simulasi Monte Carlo pada Pembangunan Gedung Ruang Kelas Belajar MAN 4 Kampar

Herianto Siahaan, Mardiaman Mardiaman

Abstract


Construction project scheduling commonly applies a deterministic approach using the Critical Path Method (CPM) to determine critical activities and project duration. However, this approach often fails to represent the uncertainty of activity durations that frequently occur during project implementation. Such uncertainty may cause deviations from the planned schedule and increase the risk of project delays. Therefore, a probabilistic approach is required to analyze project duration variability more realistically. This study aims to analyze the probability of construction project completion time by integrating the Critical Path Method and Monte Carlo simulation. The case study was conducted on the construction project of the MAN 4 Kampar classroom building with a planned duration of 244 days. The analysis began with developing a project network and identifying the critical path using CPM. The variability of activity durations on the critical path was then modeled using a triangular probability distribution and analyzed through Monte Carlo simulation using Oracle Crystal Ball with 1000 iterations. The simulation results indicate that the project duration follows a probabilistic distribution ranging from 199.13 days to 214.99 days. The project duration at the P50 probability level is 207.58 days, while the P80 and P90 levels are 209.76 days and 210.76 days, respectively. These findings demonstrate that the probabilistic approach provides a more comprehensive representation of project duration variability compared with the deterministic approach. Therefore, the integration of CPM and Monte Carlo simulation is recommended as a probabilistic analysis method in the planning and control of construction project schedules to anticipate project duration uncertainty.

Keywords


Critical Path Method, Monte Carlo Simulation, project duration uncertainty, probabilistic scheduling, construction project management

Full Text:

PDF

References


Acebes, F., Pajares, J., Manuel, J., & López-paredes, A. (2014). A new approach for project control under uncertainty Going back to the basics. International Journal of Project Management, 32(1), 423–434. https://doi.org/http://dx.doi.org/10.1016/j.ijproman.2013.08.003

Durdyev, S. (2020). Review of construction journals on causes of project cost overruns. Engineering, Construction and Architectural Management, 2(2017), 1–10. https://doi.org/10.1108/ECAM-02-2020-0137

El-dash, K. M. M., Ramadan, O. M. O., & Youssef, W. M. M. A. (2019). Duration Prediction Models for Construction Projects in Middle East. Engineering, Technology & Applied Science Research, 9(2), 3924–3932.

Hartmann, V., Lahmer, T., & Smarsly, K. (2017). Project scheduling under uncertainty and resource constraints. Proc. Appl. Math. Mech, 840, 839–840. https://doi.org/10.1002/pamm.201710387

Ichsan, M., Isvara, W., & Karim, S. (2025). Monte Carlo Simulation for Enhancing the Schedule Completion Forecast of Jakarta Central Railway Station Construction Project. Applied Science, 15(13), 1–20. https://doi.org/https://doi.org/10.3390/app15137464

Jian-wen, H., & Xing-xia, W. (2009). Risk Analysis of Construction Schedule Based on PERT and MC Simulation. International Conference on Information Management, Innovation Management and Industrial Engineering, 1(2), 150–153. https://doi.org/10.1109/ICIII.2009.195

Khamooshi, H., & Golafshani, H. (2014). EDM: Earned Duration Management, a new approach to schedule performance management and measurement. International Journal of Project Management, 32(6), 1019–1041. https://doi.org/10.1016/j.ijproman.2013.11.002

Kim, B., & Pinto, J. K. (2019). What CPI = 0.85 Really Means: A Probabilistic Extension of the Estimate at Completion. Journal of Management in Engineering, 35(2), 1–30. https://doi.org/10.1061/(asce)me.1943-5479.0000671

Kim, B., & Reinschmidt, K. F. (2009). Probabilistic Forecasting of Project Duration Using Bayesian Inference and the Beta Distribution. Journal Of Construction Engineering And Management, 1(March), 178–186.

Koulinas, G. K., Xanthopoulos, A. S., Tsilipiras, T. T., & Koulouriotis, D. E. (2020). Schedule Delay Risk Analysis in Construction Projects with a Simulation-Based Expert System. Buildings, 10(134), 1–19. https://doi.org/doi:10.3390/buildings10080134

Lee, H., Shin, J., Park, M., & Ryu, H. (2009). Probabilistic Duration Estimation Model for High-Rise Structural Work. Journal Of Construction Engineering And Management, 2(December), 1289–1298. https://doi.org/10.1061/共ASCE兲CO.1943-7862.0000105

Mardiaman, & Siregar, J. (2023). Analisis Deviasi Kemajuan Pekerjaan Berdasarkan Persentase Durasi Waktu Pada Pekerjaan Konstruksi Bangunan. Menara : Jurnal Teknik Sipil, 18(152), 59–65.

Roberta, I., & Mardiaman. (2025). Evaluasi Perbandingan Kinerja Proyek Konstruksi Pabrik Kelapa Sawit Menggunakan Metode Earned Value : Studi Kasus Dua Proyek Pabrik Kelapa Sawit. Jurnal Arsip Rekayasa Sipil Dan Perencanaan (JARSP), 8(3), 242–249. https://doi.org/https://doi.org/10.24815/jarsp.v8i3.46033

Sadeghi, N., Fayek, A. R., & Pedrycz, W. (2010). Fuzzy Monte Carlo Simulation and Risk Assessment in Construction. Computer-Aided Civil and Infrastructure Engineering, 25(4), 238–252. https://doi.org/10.1111/j.1467-8667.2009.00632.x

Saputra, N., Handayani, E., & Dwiretnani, A. (2021). Analisa Penjadwalan Proyek dengan Metode Critical Path Method (CPM) Studi Kasus Pembangunan Gedung Rawat Inap RSUD Abdul Manap Kota Jambi. Jurnal Talenta Sipil, 4(1), 44. https://doi.org/10.33087/talentasipil.v4i1.48

Sari, D. M., Agustappraja, H. R., Arif, S., & Hepiyanto, R. (2025). Biaya dan Waktu Proyek Gedung Satnarkoba dengan Metode CPM dan Metode PERT. Jurnal Talenta Sipil Vol, 8(2), 900–906. https://doi.org/10.33087/talentasipil.v8i2.969

Setiawan, A., & Labombang, M. (2024). Scheduling The Construction of Low-Income Community Houses in Palu City Using the Probabilistic Duration Method Scheduling The Construction of Low-Income Community Houses in Palu City Using the Probabilistic Duration Method. IICESSD-2023, 1–8. https://doi.org/10.1088/1755-1315/1355/1/012013

Shinde, R. (2021). Probabilistic Integration of Cost and Schedule Risk Management in Construction Engineering : A Monte Carlo Framework for Enhanced Owner Decision-Making. Journal of Informatics Education and Research, 1(3), 67–72.

Sweis, G., Sweis, R., Abu Hammad, A., & Shboul, A. (2008). Delays in construction projects: The case of Jordan. International Journal of Project Management, 26(6), 665–674. https://doi.org/10.1016/j.ijproman.2007.09.009

Utari, R. P., Wahyudiono, S., Amal, A. S., & Ardian, L. (2025). G-Tech : Jurnal Teknologi Terapan Cost and Time Control Using The Earned Value Concept ( EVM ) Method : G-Tech : Jurnal Teknologi Terapan, 9(4), 2229–2239.

Vanhoucke, M. (2015). On The Use Of Schedule Risk Analysis For Project Management. The Journal Of Modern Project Management, 1(April), 109–117.

Xiao, X., Wang, F., Li, H., & Skitmore, M. (2018). Modelling The Stochastic Dependence Underlying Construction Cost And Duration. Journal of Civil Engineering and Management, 24(6), 444–456.

Xie, W., Deng, B.-C., Yin, Y., Lv, X., & Deng, Z. (2022). Critical Factors Influencing Cost Overrun in Construction Projects: A Fuzzy Synthetic Evaluation. Buildings, 12(11), 2028. https://doi.org/10.3390/buildings12112028




DOI: http://dx.doi.org/10.33087/talentasipil.v9i2.1337

Refbacks

  • There are currently no refbacks.


Creative Commons License
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

Jurnal Talenta Sipil, Faculty of Engineering, Batanghari University
Adress: Fakultas Teknik, Jl.Slamet Ryadi, Broni-Jambi, Kec.Telanaipura, Kodepos: 36122, email: talentasipil.unbari@gmail.com


Creative Commons License This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.