Risiko Ketidakpastian Durasi dengan Metode PERT pada Pekerjaan Struktur Atas Proyek Gedung Bertingkat

Alfira Dwi Karimah, Lila Ayu Ratna Winanda, Munasih Munasih, Mohammad Erfan

Abstract


Uncertainty in duration often occurs in superstructure work due to the interdependence of activities and dynamic changes in field conditions. Deterministic scheduling methods such as the Critical Path Method (CPM) are considered incapable of representing duration variations realistically, thus requiring a probabilistic scheduling approach. Therefore, this study aims to analyze the duration of superstructure work using the Program Evaluation and Review Technique (PERT) method supported by scheduling using Microsoft Project software. The PERT method was applied through three time estimates, namely optimistic time, most likely time, and pessimistic time, with data obtained through interviews and questionnaires with experienced experts in the field of construction. Based on the analysis results, the actual duration of the project implementation reached 487 days, while the expected duration based on the PERT method was 235 days with a Z-score value of 9.79, resulting in a 47% probability of completion within the expected duration. The significant difference between the ideal duration and the actual conditions in the field indicates a 53% risk of delay that must be faced by the implementer, so that the results of this study can be used as a basis for consideration in determining a more realistic and tolerable project duration. More accurate time planning can be achieved by reducing the risk of delays through controlling and accelerating critical path activities, thereby optimizing the chances of project completion.

Keywords


Building Construction; Project Duration; Program Evaluation and Review Technique;Time Optimization; Upper Structure

Full Text:

PDF

References


Aprillia, S.C. and A, Q.Q. (2023) “Optimalisasi Biaya dan Waktu Pelaksanaan Pembangunan rumah tinggal di Kecamatan Rantau Pulung Kutai Timur menggunakan Critical Path Method ( CPM ) dan Program Evaluation and Review Technique ( PERT ),” jurnal.fmipa.unmul.ac.id, 2(1), pp. 11–24.

Dwiretnani Annisaa, Handayani Elvira, S.N. (2023) “Evaluasi Penjadwalan Waktu Proyek Pembangunan Gedung Menggunakan Critical Path Method (CPM) Annisaa,” Jurnal Talenta Sipil, 6(1995), pp. 391–400. Available at: https://doi.org/10.33087/talentasipil.v6i2.334.

Fahri, M.I., Rakhmawati, F. and Panjaitan, D.J. (2024) “Optimasi Waktu Dan Biaya Pembangunan Box Underpass ProyekJalan Tol Ruas Sigli-Banda Aceh Dengan Menggunakan MetodePert Dan Evm,” Jurnal Matematika dan Pendidikan Matematika, 7, pp. 44–56.

Islam, U. and Agung, S. (2025) “Analisis Penjadwalan Proyek Menggunakan Metode Pert Dan Fast Track Dari Hasil Pembangunan Kek Mandalika Paket 1 Nano Suharyono 1 ,Rachmat Mudiyono 2 ,Sumirin 3 .,” Journal of Mandalika Literature, 6(3), pp. 917–923.

Kartika, D. et al. (2025) “Analisis Optimasi Percepatan Waktu Proyek Konstruksi untuk Mengatasi Keterlambatan Jadwal,” Jurnal Infomanpro, 14(2), pp. 63–71.

Kasus, S. et al. (2022) “Analisis Perbandingan Penjadwalan Proyek Dengan Metode CPM , PERT , KURVA-S,” Media Komunikasi Ilmiah Dibidang Teknik e-ISSN, 23(1), pp. 77–89.

Kojongian, J., Dundu, A. and Arsjad, T. (2025) “Penerapan Metode PERT Untuk Penjadwalan Gedung Kuliah FMIPA,” 23(91).

Langkun, C.N. V et al. (2025) “Penerapan Metode PERT Untuk Penjadwalan Gedung Kuliah FMIPA Jurusan Farmasi Universitas Sam Ratulangi,” 23(91).

Lauriska, N.F., Negoro, Y.P. and Priyana, E.D. (2025) “Analisis Waktu Dan Biaya Proyek Sistem Sie Water Menggunakan Metode CPM DAN PERT,” 4(4), pp. 1550–1558.

Leimena, I.M. and Fahmi (2024) “Percepatan waktu menggunakan metode cpm dan pert pada proyek instalasi pipa dan mesin pompa swimming pool buin batu school,” Jurnal Ilmiah Teknologi Informasi Terapan, 11(1).

Lugina, L., Suseno, A. and Sunakalis Geraldo Cikal (2022) “Penerapan Metode Project Evaluation and Review Technique ( PERT ) dan Critical Path Method ( CPM ) terhadap Pembangunan Gedung,” Jurnal Pendidikan Tambusai, 6, pp. 880–888.

Marpaung, R., Daulay, I.N. and Tambunan, V. (2022) “Optimalisasi penjadwalan proyek pembangunan pabrik kelapa sawit dengan menggunakan metode PERT dan CPM pada PT . Bintang Riski Abadi,” 17, pp. 117–127.

Nanda, M.P., Kurniawati, M. and Riswanto, S. (2023) “Penggunaan Metode Project Evaluation Review Technique ( PERT ) Dalam Evaluasi Perencanaan,” Jurnal Teknik Sipil, 17(3), pp. 163–173. Available at: https://doi.org/10.24002/jts.v17i3.7181.

Ngestiaji, R.D.P., Aditama, V. and Winanda, L.A.R. (2025) Penerapan Metode Pert Pada Penjadwalan Pembangunan Tugu Alun-Alun Kota Mojokerto. Institut Teknologi Nasional Malang.

Sari, D.M. et al. (2025) “Biaya dan Waktu Proyek Gedung Satnarkoba dengan Metode CPM dan Metode PERT,” Jurnal Talenta Sipil, 8(2), p. 900. Available at: https://doi.org/10.33087/talentasipil.v8i2.969.

Shah, T.A. and Suprapto, B.A.R. (2024) “Optimasi Manajemen Waktu Proyek Menggunakan Metode Cpm Dan Pert Pada Pelaksanaan Pekerjaan Struktur Rumah Sakit Birrul Walidain Kabupaten Lamongan,” Jurnal Rekayasa Sipil, 14(2), pp. 96–103.

Wahyudiono, S. et al. (2023) “Penerapan Metode Program Evaluation and Review Technique ( PERT ) Pada Proyek Malang Creative Center ( MCC ) Berdasarkan Building Information Modelling ( BIM ) Application Of the Program Evaluation and Review Technique ( PERT ) Method in The Malang Creati,” Media Teknik Sipil, 21(2), pp. 66–76.




DOI: http://dx.doi.org/10.33087/talentasipil.v9i1.1249

Refbacks

  • There are currently no refbacks.


Creative Commons License
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

Jurnal Talenta Sipil, Faculty of Engineering, Batanghari University
Adress: Fakultas Teknik, Jl.Slamet Ryadi, Broni-Jambi, Kec.Telanaipura, Kodepos: 36122, email: talentasipil.unbari@gmail.com


Creative Commons License This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.