Manajemen Waktu dan Biaya Proyek dengan Sistem Crash Menggunakan Microsoft Project pada Peningkatan Jalan Soko – Karangbinangun

Moch. Diyas Nur Hidayat, Rasio Hepiyanto, Rio Rahma Dhana

Abstract


Time and cost management play an important role in the success of a construction project. Therefore, project planning and scheduling must be done carefully before implementation begins. The Soko – Karangbinangun road improvement project faces a number of challenges, especially in terms of time management. In this project, the work that was supposed to start on September 3 according to the contract, was delayed and only started on September 23. This condition has the potential to cause delays in project completion. This study aims to compare the results of theoretical calculations with the factual conditions in the field, and to evaluate the possibility of accelerating the project schedule without sacrificing cost efficiency. The acceleration method used in this study is the overtime system with variations in duration of 1, 2, and 3 hours. Ms. Project is used as a tool to identify the critical path in the project. The results of the analysis show that out of 9 initial work items, there are 8 items included in the critical path. With a variation of 1 hour overtime, the project duration can be accelerated to 68 days, 10 days shorter than the normal duration of 78 days, with a crashing cost of Rp. 1,233,684,874.50 from the normal cost of Rp. 1,229,803,328.00. For 2-hour overtime, the work can be completed in 59 days, 19 days faster than the normal duration, with a crashing cost of Rp. 1,246,809,926.00. While for 3-hour overtime, the project can be completed in 51 days, or 27 days faster than the normal duration, with a crashing cost of Rp. 1,264,842,460.50. From the results of the analysis that have been known, it can be concluded that the 2-hour overtime variation method is more effective to apply.

Keywords


management; time; cost; acceleration; schedule; efficiency; overtime; Ms. Project.

Full Text:

PDF

References


Al-bab, U., & Hepiyanto, R. (2024). Analisa Manajemen Waktu Pekerjaan Renovasi Pembangunan Cafe Terakota. Jurnal Talenta Sipil, 7(1), 142. https://doi.org/10.33087/talentasipil.v7i1.400

Ali, M. K. (2024). STRATEGIC OVERTIME IMPLEMENTATION: ASSESSING CRASH TIME, CRASH COST AND COST SLOPE IN THE CONSTRUCTION OF KADIRI UNIVERSITY’S 4-STORY BUILDING. ISSN(2), 41–47. https://doi.org/10.56127/ijst

Anwar F. (2019). ANALISIS CRASH PROGRAM MENGGUNAKAN MICROSOFT PROJECT PADA PENINGKATAN JALAN SP.LAGO - SOREK I KABUPATEN PELALAWAN.

Dewanto, W. P., & Yustisia, H. (2024). Analysis of Project Time and Cost using the Crash Program Approach (Vol. 11, Issue 3). http://cived.ppj.unp.ac.id/index.php/CIVED

Dwiretnani, A., Handayani, E., & Saputra, N. (2023). Evaluasi Penjadwalan Waktu Proyek Pembangunan Gedung Menggunakan Critical Path Method (CPM). Jurnal Talenta Sipil, 6(2), 391. https://doi.org/10.33087/talentasipil.v6i2.334

Erlina, Iskandar, M. R., & Cahya Nugraha, O. (2022). ANALISA OPTIMALISASI WAKTU DAN BIAYA PADA PEMBANGUNAN RUSUNAWA GEMAWANG YOGYAKARTA DENGAN PROGRAM MICROSOFT PROJECT. 1. https://jurnal.ucy.ac.id/index.php/CivETech/issue/archive

Jayantari, M. W., Predana, I. M. A., & Wade, Y. R. (2022). Analisis Biaya Serta Percepatan Durasi Proyek Menggunakan Metode Crashing dengan Sistem Waktu Gilir Kerja dan Lembur (Studi Kasus: Puskesmas Wolowaru, Kabupaten Ende). Reinforcement Review in Civil Engineering Studies and Management, 1(1), 20–26. https://doi.org/10.38043/reinforcement.v1i1.4098

Jazuli, M., & Dhana, R. R. (2024). Analisis Biaya dan Waktu pada Proyek Jembatan (Studi Kasus Proyek Pembangunan Jembatan Candisari Sambeng Kabupaten Lamongan) dengan Menggunakan Metode Earned Value. Jurnal Talenta Sipil, 7(1), 73. https://doi.org/10.33087/talentasipil.v7i1.376

Luqman Hakim, A., Yulianto, T., & Wahyu Nugroho, M. (2023). Optimalisasi Waktu dan Biaya Menggunakan Metode Crashing Program pada Proyek Gedung BPJS Tulungagung. BRILIANT: Jurnal Riset Dan Konseptual, 8(1). https://doi.org/10.28926/briliant.v8i1

Mahendra, M. O., Saputro, T. E., & Putra, A. F. S. (2025). Penerapan Microsoft Project dalam Metode Crashing Terhadap Waktu dan Biaya. Jurnal Teknik Industri Terintegrasi, 8(2), 1908–1918. https://doi.org/10.31004/jutin.v8i2.44080

Malifa, Y., Dundu, A. K. T., & Malingkas, G. Y. (2019). ANALISIS PERCEPATAN WAKTU DAN BIAYA PROYEK KONSTRUKSI MENGGUNAKAN METODE CRASHING (STUDI KASUS: PEMBANGUNAN RUSUN IAIN MANADO). Jurnal Sipil Statik, 7(Juni), 681–688.

Nardiansyah, A., Widi, D., & Intansari, A. (2022). Optimasi Waktu dan Biaya dengan Metode Crashing pada Proyek Pembangunan Jalan Simp. 4 Kaliorang-Talisayan Kalimantan Timur (Vol. 04).

Raranta H, Arsjad T, & Pratasis P. (2024). Optimalisasi Biaya Dan Waktu Dengan Metode Time Cost Trade Off. In Tahun (Vol. 22, Issue 88).

Schulz N, & Putra F. (2021). ANALISIS KETERLAMBATAN PROYEK PADA PEMBANGUNAN TANGGUL. In Jurnal Kajian Teknik Sipil (Vol. 6, Issue 02).

Yuliana, N. P. I., Suartika Putra, I. G. P. A., Yuni, N. K. S. E., & Sudiarta, I. K. (2024). Kajian Biaya Penerapan Sistem Manajemen Keselamatan Konstruksi Pada Proyek Villa Banana di Kabupaten Badung. Jurnal Talenta Sipil, 7(1), 173. https://doi.org/10.33087/talentasipil.v7i1.424

Zulhijjah, P., Djamaluddin, R., & Purnama Sari, D. (2022). Analisis Percepatan Proyek Menggunakan Metode Crashing dengan Penambahan Jam Kerja Lembur Optimum. In Jurnal Ilmiah Teknik UNIDA ) P (Vol. 3, Issue 1).




DOI: http://dx.doi.org/10.33087/talentasipil.v8i2.955

Refbacks

  • There are currently no refbacks.


Creative Commons License
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

Jurnal Talenta Sipil, Faculty of Engineering, Batanghari University
Adress: Fakultas Teknik, Jl.Slamet Ryadi, Broni-Jambi, Kec.Telanaipura, Kodepos: 36122, email: talentasipil.unbari@gmail.com


Creative Commons License This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.