Optimalisasi Waktu dan Biaya Proyek Gelora Ahmad Yani Mojokerto Menggunakan Metode Time Cost Trade Off

Susila Bayu Aji, A'izzatul Khiyana, Totok Yulianto, Titin Sundari

Abstract


The Gelora Ahmad Yani Infrastructure Project in Mojokerto experienced delays from week 5 to week 7, which could extend the project duration and increase construction costs. These delays required a measurable time and cost control evaluation to ensure more efficient project completion. This study aimed to determine the most optimal acceleration alternative for the project using the Time Cost Trade Off (TCTO) method. The research data consisted of the Budget Plan, project schedule, progress reports, working-hour data, and heavy equipment data. The analysis was conducted on critical path activities by comparing acceleration scenarios involving 1, 2, 3, and 4 hours of overtime work and the addition of a mini roller. The results show that the normal project condition had a duration of 90 days with a total cost of IDR 870,542,000.00. The most optimal alternative was the addition of heavy equipment, which produced a final duration of 25 days, representing an acceleration of 65 days or 72.22%. The total project cost decreased to IDR 843,848,152.79, with a saving of IDR 26,693,847.21 or 3.07% compared with the normal cost. Therefore, adding a mini roller is recommended as a more effective acceleration strategy, particularly for critical paving activities.

Keywords


construction project; project duration; project cost; critical path; time cost trade off

Full Text:

PDF

References


Agustus, N., Saifuddin, A., Ridwan, A., & Damara, B. (2025). Jurnal Talenta Sipil ( Earned Value Management ) pada Proyek Pembangunan,3 8(2), 755–762. https://doi.org/10.33087/talentasipil.v8i2.942.

Ajeng, J., Dwi, K. T., Gunasti, A. (2023). Penerapan Manajemen Konstruksi Pada Tahap Kontroling Proyek Pengolahan Dan Pengembangan Sistem Penyediaan Air Minum Di Desa Silo Kecamatan Silo. Jurnal Smart Teknologi, 4(5), 659–666. https://jurnal.unmuhjember.ac.id/index.php/JST/article/view/23212.

Hidayat, M. D. N., Hepiyanto, R., Dhana, R. R. (2025). Manajemen Waktu dan Biaya Proyek dengan Sistem Crash Menggunakan Microsoft Project pada Peningkatan Jalan Soko – Karangbinangun. Jurnal Talenta Sipil, 8(2), 947–953. https://doi.org/10.33087/talentasipil.v8i2.955.

Ikhtisholiyah, Wardana, M. H. I., Agustiar, I. (2025). Penerapan Metode Cpm Dan Time Cost Trade Off Dalam Mengelola Waktu Serta Biaya Proyek Konstruksi X. Jurnal Ilmiah Teknik Sipil, 14(1), 9–24. http://dx.doi.org/10.46930/tekniksipil.v11i2.5578.

Intan, A, P., Yulianto, T., Nugroho, M. W. (2025). Analisis Optimasi Waktu Dan Biaya Pada Proyek Rehabilitasi Sarana Dan Prasarana Gedung Sekolah Dengan Metode Time Cost Trade Off. Jurnal Ilmiah Reaktip, 05(01). 39 - 45. https://doi.org/10.33752/reaktip.v5i01.9875.

Jhon, O., Duwit, W., & Sarya, G. (2024). Method On The Austinov Surabaya Hotel Construction. Journal of Scientech Research and Development, 6(1), 780–789. doi:10.56670/jsrd.v6i1.404.

Khiyana, A., Sundari, T., Yulianto, T., Nugroho, M. W., & Agung, A. I. (2025). Analysis And Risks Fast Track And Crash Program Method On Building Project. Jurnal Pensil: Pendidikan Teknik Sipil, 14(1), 154–168. https://doi.org/10.21009/jpensil.v14i1.50234.

Kuncoro, B. M. C., & Octavia, T. (2025). Analisis Faktor-faktor Keterlambatan Waktu pada Proyek Konstruksi Gedung Bertingkat di Indonesia terhadap Profesionalisme dan Etika Kerja. Jurnal Dimensi Insinyur Profesional, 2(2), 7–14. https://doi.org/10.9744/jdip.2.2.7-14.

Lestari, I. N., & Lubis, Z. (2023). Analisis Percepatan Proyek Menggunakan Metode Time Cost Trade Off Untuk Pekerjaan Tanah. Jurnal Gradasi Teknik Sipil, 7(2), 150–156. https://doi.org/10.31961/gradasi.v7i2.1442.

Mudhoffar, F., & Prafitasiwi, A. G. (2024). Pengendalian Waktu dan Biaya pada Proyek Gedung TPQ 2 Lantai dengan Metode Time Cost Trade Off ( TCTO ). Jurnal Teknik Sipil dan Lingkungan, 01(1), 1–8. https://doi.org/10.30587/jtsl.v1i1.7405.

Oktaviani, I. (2023). Review Perbandingan Produktivitas Alat -Alat Berat Pekerjaan Timbunan Borrow Material Pada Proyek Jalan Tol Jakarta-Cikampek Selatan Ii. Jurnal Ismetek, 16(1), 42–45. /https://ismetek.itbu.ac.id/index.php/jurnal/article/view/225.

Pemerintah Republik Indonesia. (2021). Peraturan Pemerintah Republik Indonesia Nomor 35 Tahun 2021 tentang Perjanjian Kerja Waktu Tertentu, Alih Daya, Waktu Kerja dan Waktu Istirahat, dan Pemutusan Hubungan Kerja.

Ramadhani, M. I., & Prafitasiwi, A. G. (2025). Analisis Percepatan Proyek Pembangunan Jalan Beton Tahap II Di Perumahan Citra Sari Regency Dengan Metode Time Cost Trade Off ( TCTO ). Jurnal Teknik Sipil dan Rekayasa, 2(1), 23–32. https://doi.org/10.30587/jtsl.v2i1.

Revinanda, R. F., Kustiani, I., Siregar, A. M., & Usman, K. (2023). Analisis Percepatan Pelaksanaan Proyek Pembangunan Gedung Feb Universitas Lampung Tahap II 2022 Metode Time Cost Trade Off. Jurnal Momen Teknik Sipil, 6(2), 94-102. https://doi.org/10.35194/momen.v6i02.3418.

Soeharto, I. (1999). Manajemen proyek: Dari konseptual sampai operasional. Erlangga.

Syahada, K. N., Rindo, G., Santosa, A. W. B., Prasetyo, A. N. (2024). Analisis Reschedule Keterlambatan Proyek Reparasi Dua Kapal Dengan Metode Critical Path Method ( CPM ) Dan Time Cost Trade Off ( TCTO ) Pada KM . Kendhaga Nusantara 4 Dan TB . Sorowako Star. Jurnal Integrasi, 16(2), 156–164. https://doi.org/10.30871/ji.v16i2.845.1

Widiastuti, E., Sugiarti, M. F., Yuliana, C., & Karim, A. (2025). Optimasi Waktu dan Biaya Proyek Gelanggang Olahraga. Jurmateks: Jurnal Manajemen Teknologi dan Teknik Sipil, 8(1), 79-92 https://doi.org/10.30737/jurmateks.v8i1.6597.

Werdana, S. D., & Priyanto, B. (2023). Analisis Percepatan Waktu Dan Biaya Proyek Konstruksi Dengan Penambahan Jam Kerja ( Lembur ) Menggunakan Metode Time Cost Trade Off. Journal of Comprehensive Science, 2(7), 1976–1980. https://doi.org/10.59188/jcs.v2i7.423.




DOI: http://dx.doi.org/10.33087/talentasipil.v9i2.1418

Refbacks

  • There are currently no refbacks.


Creative Commons License
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

Jurnal Talenta Sipil, Faculty of Engineering, Batanghari University
Adress: Fakultas Teknik, Jl.Slamet Ryadi, Broni-Jambi, Kec.Telanaipura, Kodepos: 36122, email: talentasipil.unbari@gmail.com


Creative Commons License This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.