Manajemen Biaya dan Waktu pada Pekerjaan Pembangunan Gedung Serba Guna Lontar Surabaya Menggunakan Metode CPM dan PERT

Rasio Hepiyanto, Rio Rahma Dhana, Galang Syahri Romadhon

Abstract


A project is an activity carried out to produce services that have a specific schedule. In the implementation of the project, there is a discrepancy between planning and realization, both in terms of time and cost. Scheduling is determined by the relationship of a project activity that is made very detailed and accurate. Especially in the construction of the Lontar Surabaya Multipurpose Building. The aim is to analyze to find out the processing of the application of the CPM (Critical Path Method) and PERT (Project Evaluation and Review Technique) methods. These two methods identify activities that affect project completion to predict costs, duration, critical paths and probabilities of a project. The research was conducted quantitatively by collecting primary and secondary data and through interviews with results in the field. The results of the research implementation show that the critical path in the project occurs in activities, A – B – H – I – J – K – M – N – F – E – O – O1 – O2 – O3 – G – Q – P – T – T1 – T2 – Z – Z1 – Z2 – Z3 – Z4 – Z5. Witg having a total duration of 79 days using the CPM and PERT methods, there were cost and time savings of 11 days.

Keywords


Cost, Time, Critical Path, Project Scheduling, CPM, PERT.

Full Text:

PDF

References


Abdurrasyid, Luqman, A. H., & Indrianto. (2019). Implementasi Metode PERT dan CPM pada Sistem Informasi Manajemen Proyek Pembangunan Kapal. In Jurnal Ilmu Komputer dan Informatika (Vol. 28, Issue 1).

Adebowale, S. A., & Oluboyede, E. D. (2011). Network analysis and building construction: Implications for timing and costing of activities. Journal of Civil Engineering and Construction Technology, 2(5), 90–100. http://www.academicjournals.org/jcect

Agustiar, I., & Handrianto, R. (2018). Evaluasi Penjadwalan Proyek Menggunakan Metode CPM DAN Kurva S (Studi Kasus : Pembangunan Gedung Perpustakaan SMK N 1 “XX”, Gresik). In Jurnal keilmuan dan Terapan Teknik (Vol. 07).

Al-bab, U., & Hepiyanto, R. (2024). Analisa Manajemen Waktu Pekerjaan Renovasi Pembangunan Cafe Terakota. Jurnal Talenta Sipil, 7(1), 142. https://doi.org/10.33087/talentasipil.v7i1.400

Ali Murdani Lubis, Endang Suhendar, & Puji Suharmanto. (2021). Optimasi Penjadwalan Proyek Pembangunan Jalan Tol Becakayu Seksi 1BC Dengan Menggunakan Metode CPM Dan PERT. In Universitas Sahid Jakarta.

arianto A. (2010). Eksplorasi Metode Bar Chart, CPM, PDM, PERT, Line Of Balance Dan Time Chainage Diagram Dalam Penjadwalan Proyek Konstruksi.

Burhan, M. I., Singkeruang, A. W. T. F., & Alam, N. (2023). Implementasi Metode PERT dan CPM pada Proyek Integrasi Sistem Informasi Kontrol Pemantauan Kondisi Lalu Lintas. BUGIS: Journal of Business, Technology, & Social Science.Dwiretnani, A., Handayani, E., & Saputra, N. (2023). Evaluasi Penjadwalan Waktu Proyek Pembangunan Gedung Menggunakan Critical Path Method (CPM). Jurnal Talenta Sipil, 6(2), 391. https://doi.org/10.33087/talentasipil.v6i2.334

Ernawati, & Purwanto, D. (2023). Analisa Waktu Pelaksanaan dan Biaya Pada Proyek Pembangunan Gedung Serbaguna Agross Terra Land. INTER TECH, 1(2), 30–43. https://doi.org/10.54732/i.v1i2.1062

Hadicara D. (2023). Penerapan Metode Pert Dan Cpm Pada Pembangunan Jalan Tinjomoyo – Sekaran.

Naura Mutia Astari, Ade Momon Subagyo, & Kusnadi. (2021). Perencanaan Manajemen Proyek Dengan METODE CPM (Critical Path Method) Dan Pert (Program Evaluation And Review Technique). In Jurnal Konstruksia | (Vol. 13).

Sa’adah, N., Iqrammah, E., Rijanto, T., & Kegiatan, A. (2021). Evaluasi Proyek Pembangunan Gedung Stroke Center (Paviliun Flamboyan) Menggunakan Metode Critical Path Method (CPM) Dan Crashing Evaluation of building construction Stroke Center (Paviliun Flamboyan) using the Critical Path Method (CPM) And Crashing Method.

Setiawan, D. C., & Ridwan, A. (2021). Optimalisasi Penjadwalan Proyek Pembangunan Gedung Puskesmas Badas Menggunakan Critical Path Method-Project Evaluation and Review Technique (CPM-PERT). 4. https://doi.org/10.30737/jurmateks

Stie, W., Tuban, M., & Syaikhudin, A. Y. (2020). Studi Penerapan Critical Path Metode (CPM) Pada Proyek Pembangunan Pabrik Semen Rembang Pt Semen Gresik. In Journal of Management and Accounting (Vol. 3, Issue 2).

Tsalist Iluk, Ahmad Ridwan, & Sigit Winarto. (2020). Penerapan Metode CPM Dan PERT Pada Gedung Parkir 3 Lantai Grand Pannglima Polim Kediri. https://doi.org/10.30737/jurmateks

Wattimury, H., Walangitan, D. R. O., & Sibi, M. (2015). Identifikasi Faktor-Faktor Cost Overrun Biaya Overhead Pada Proyek Pembangunan Manado Town Square III. Jurnal Sipil Statik, 3(4), 260–267.




DOI: http://dx.doi.org/10.33087/talentasipil.v9i1.1058

Refbacks

  • There are currently no refbacks.


Creative Commons License
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

Jurnal Talenta Sipil, Faculty of Engineering, Batanghari University
Adress: Fakultas Teknik, Jl.Slamet Ryadi, Broni-Jambi, Kec.Telanaipura, Kodepos: 36122, email: talentasipil.unbari@gmail.com


Creative Commons License This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.