Penerapan Metode PDM dan Pert pada Proyek Pembangunan Pusat Layanan Haji dan Umroh Terpadu Kota Balikpapan

Azan Yamani Purwanto, Gunaedy Utomo, Reno Pratiwi

Abstract


The construction of the Integrated Hajj and Umrah Service Center (PLHUT) in Balikpapan City is a construction project that requires effective time management to ensure timely completion. This study aims to analyze the critical path and the probability of successful project completion using the Precedence Diagram Method (PDM) and Program Evaluation and Review Technique (PERT). The PDM method is utilized to identify the project’s critical path by structuring the interdependencies of work items, visualized through a network diagram. Meanwhile, the PERT method is employed to calculate the probability of project completion within the planned duration, taking into account the uncertainties in activity durations. Based on the analysis results, the PLHUT construction project in Balikpapan City, with a planned duration of 160 days, contains several critical activities that require careful resource management and scheduling. The probability calculation using the PERT method indicates a high likelihood of completing the project on time. Thus, the combination of PDM and PERT methods serves as an effective approach in construction project management to enhance efficiency and schedule accuracy.

Keywords


Project Management; PDM; PERT; Critical Path; Completion Probability.

Full Text:

PDF

References


Asrulla et al. (2023) ‘Populasi dan Sampling (Kuantitatif), Serta Pemilihan Informan Kunci (Kualitatif) dalam Pendekatan Praktis’, Jurnal Pendidikan Tambusai, 7(3), pp. 26320–26332.

Aulia, S.S. (2021) Analisis Penjadwalan Proyek Gedung Menggunakan Metode Cpm-Pert ( Critical Path Method-Program Evaluation And Review Technique ) ( Analysis Of Building Project Scheduling Using The Cpm-Pert Method ).

Balikpapan, K.A. (2024) ‘Diresmikan Menag, Kini Masyarakat Kaltim Punya 2 Gedung PLHUT Baru’, inibalikpapan.com.

Direktorat Jenderal Kependudukan dan Pencatatan Sipil Kementerian Dalam Negeri (2024) ‘Dukcapil: Jumlah penduduk Indonesia 282 juta jiwa pada semester I-2024’, ANTARA KALSEL.

Fazis, M. and Tugiah, T. (2022) ‘Perencanaan Proyek dan Penjadwalan Proyek’, Jurnal Sosial Teknologi, 2(12), pp. 1365–1377. Available at: https://doi.org/10.59188/jurnalsostech.v2i12.517.

Hutabarat, E.M. et al. (2023) ‘Microsoft Project Pada Proyek Pembangunan Gedung’, pp. 986–995.

Hutomo, I.S. and Rohman, M.A. (2021) ‘Penjadwalan Probabilistik pada Proyek Jalur Lintas Selatan LOT. 6’, Jurnal Teknik ITS, 10(2), pp. 202–209. Available at: https://doi.org/10.12962/j23373539.v10i2.74300.

Mahyuddin et al. (2023) Manajemen Proyek Konstruksi.

Mardiani, G.T. (2018) ‘Analisis Estimasi Waktu Penyelesaian Proyek Perangkat Lunak Menggunakan Metode PERT’, is The Best Accounting Information Systems and Information Technology Business Enterprise this is link for OJS us, 3(2), pp. 336–343. Available at: https://doi.org/10.34010/aisthebest.v3i2.1523.

Nazir, M. (2005) Metode penelitian. Ghalia Indonesia.

Pandya, M.W.Y. et al. (2024) ‘Analisis Resource Leveling Menggunakan Precedence Diagram Method (PDM) pada Gedung Mako Lanal Balikpapan’, Jurnal Talenta Sipil, 7(2), pp. 445–454. Available at: https://doi.org/10.33087/talentasipil.v7i2.488.

Populaire, S. et al. (2002) ‘Fusion of expert knowledge with data using belief functions: A case study in waste-water treatment’, in Proceedings of the 5th International Conference on Information Fusion, FUSION 2002, pp. 1613–1618. Available at: https://doi.org/10.1109/ICIF.2002.1021011.

Rahma, K.A. and Kamandang, Z.R. (2023) ‘Analisis Penjadwalan Proyek Gedung Bertingkat Menggunakan Metode CPM (Critical Path Method) dan PERT (Program Evaluation and Review Technique) (Studi Kasus: Proyek Pembangunan Tahap 1 Rumah Sakit Muhammadiyah Gresik)’, Jurnal Ilmiah Universitas Batang Hari Jambi (JIUB), 23(2), pp. 1275–1279.

Setiawan, D., Ridwan, A. and Suwarno, S. (2021) ‘Optimalisasi Penjadwalan Proyek Pembangunan Gedung Puskesmas Badas Menggunakan Critical Path Method-Project Evaluation and Review Technique (CPM-PERT)’, Jurnal Manajemen Teknologi & Teknik Sipil, 4, p. 71. Available at: https://doi.org/10.30737/jurmateks.v4i2.2011.

Tubaka, S.Y. (2017) Analisis Perencanaan Aktivitas Konstruksi Pada Pekerjaan Sarana Dan Prasarana Pltp (Pembangkit Listrik Tenaga Panas Bumi) Tulehu, Arika. Available at: https://doi.org/10.30598/arika.2017.11.2.135.

Wicaksono, M., Sugandi, R. and Alfianto, I. (2024) ‘Pengendalian Durasi Optimal pada Pembangunan Myze Hotel Sumenep Menggunakan CPM dan Metode PERT’, Bentang : Jurnal Teoritis dan Terapan Bidang Rekayasa Sipil, 12, pp. 49–62. Available at: https://doi.org/10.33558/bentang.v12i1.7323.




DOI: http://dx.doi.org/10.33087/talentasipil.v9i1.873

Refbacks

  • There are currently no refbacks.


Creative Commons License
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

Jurnal Talenta Sipil, Faculty of Engineering, Batanghari University
Adress: Fakultas Teknik, Jl.Slamet Ryadi, Broni-Jambi, Kec.Telanaipura, Kodepos: 36122, email: talentasipil.unbari@gmail.com


Creative Commons License This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.