Faktor Eksternal yang Mempengaruhi Keterlambatan Proyek Konstruksi Gedung di Kota Padang

Ade Anggrainy, Wardi Wardi, Zaitul Zaitul

Abstract


Delays in building construction projects are a common problem that can lead to cost overruns and reduced project performance. This study aims to identify and determine the influence level of external factors on delays in building construction projects in Padang City, Indonesia. A quantitative research method was employed by collecting data through questionnaires distributed to 93 respondents, including contractors, consultants, and other related stakeholders. Data analysis was conducted using the Relative Importance Index (RII) method to assess the significance of each factor, and the Analytical Hierarchy Process (AHP) supported by Expert Choice software to determine the priority of dominant factors. The results indicate that socio-cultural factors, weather conditions, and delays in the permitting process are the most influential external factors contributing to project delays in Padang City. The findings of this study are expected to provide useful insights for stakeholders in improving project planning and control to reduce the risk of delays.

Keywords


project delay, external factors, building construction, RII, Expert Choice.

Full Text:

PDF

References


Alaghbari, W., Razali, A. R., Kadir, M. R. A., Salim, A., & Ernawati. (2007). The significant factors causing delay of building construction projects in Malaysia. Engineering, Construction and Architectural Management, 14(2), 192–206.

Al-Hadithia, T. S. (2020). Investigating the delay factors of construction projects using narrative analysis approach. Iraqi Journal of Civil Engineering, 2020(1), 14–25.

Al-Najjar, J. J. (2008). Factors influencing time and cost overruns on construction projects in the Gaza Strip (Master’s thesis). Islamic University of Gaza, Gaza Strip.

Ananda, R. (2020). Analisis keterlambatan dan kualitas hasil pekerjaan pada proyek konstruksi gedung (Skripsi). Universitas Bung Hatta, Padang.

Aziz, R. F. (2013). Factors causing delay in construction projects. Alexandria Engineering Journal, 52(4), 615–620.

Bekr, G. A. (2018). Study and assessment of causes and effects of delay in large public construction projects in Jordan. International Journal of Applied Engineering Research, 13(8), 6204–6210.

Dwiantoro, D., Yoansa, A. Y., Indrayana, D. V., Mentari, S., & Widyatami, F. S. (2024). Analisis faktor penyebab keterlambatan proyek “XYZ”. Jurnal Talenta Sipil, 7(1), 200–206.

Esperance, U. (2019). Delay factors in building construction projects in Rwanda. Journal of the Korea Institute of Building Construction, 19(5), 467–475.

Hutahaean, A. (2022). Faktor-faktor keterlambatan proyek konstruksi di Papua. Jurnal Teknik Sipil, 27(1), 1–11.

Irfiadi. (2020). Analisis keterlambatan penyelesaian pekerjaan proyek konstruksi jalan Provinsi Sumatera Barat (Skripsi). Universitas Bung Hatta, Padang.

Moleong, L. J. (2012). Metodologi penelitian kualitatif. PT Remaja Rosdakarya.

Oktasani, R. (2021). Analisis faktor penyebab keterlambatan proyek konstruksi (Skripsi). Universitas Bung Hatta, Padang.

Sapulette, M. (2020). Analisis keterlambatan waktu pelaksanaan proyek konstruksi di Kota Ambon: Klasifikasi dan peringkat dari penyebab-penyebabnya. Jurnal Manumata, 6(1), 1–10.

Tafesse, S. (2021). A review on the critical factors causing delay of delivery time in construction projects. International Journal of Engineering Technologies (IJET), 6(4), 167–175.

Wirabakti, D. M. (2014). Studi faktor-faktor penyebab keterlambatan proyek konstruksi bangunan gedung. Jurnal Konstruksia, 6(1), 1–10.

Yap, J. B. H. (2020). Revisiting critical delay factors for construction: Analysing projects in Malaysia. Alexandria Engineering Journal, 60(1), 1717–1729.

Yogiswara, R. (2023). Analisis faktor penyebab keterlambatan dan perbandingan pekerjaan pemasangan bekisting aluminium dan bekisting konvensional ditinjau dari segi waktu, biaya, dan mutu. Jurnal Artesis, 3(1), 49–61.




DOI: http://dx.doi.org/10.33087/talentasipil.v9i1.1276

Refbacks

  • There are currently no refbacks.


Creative Commons License
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

Jurnal Talenta Sipil, Faculty of Engineering, Batanghari University
Adress: Fakultas Teknik, Jl.Slamet Ryadi, Broni-Jambi, Kec.Telanaipura, Kodepos: 36122, email: talentasipil.unbari@gmail.com


Creative Commons License This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.