Analisa Pemasangan Dinding Bata Ringan Sesuai AHSP Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat Tahun 2022 dan 2023 pada Pembangunan Gedung Instalasi Perawatan Intensif Terpadu (IPIT) RSUD dr. R. Koesma Tuban

Erwin Andriyani, Sugeng Hartantyo, Yosef Cahyo

Abstract


Significant changes in labor coefficients and material coefficients in the AHSP 'installation of 1m2 of 10 cm thick lightweight brick wall with ready-mixed mortar.' The purpose of this study is to test the AHSP from the years 2016, 2022, and 2023 of lightweight brick installations with a thickness of 10 cm using ready-mixed mortar, as well as to compare the HSPK of lightweight brick with kumbung brick based on the results of the construction study of the IPIT RSUD dr. R. Koesma Tuban building. The research method uses a comparison of labor and material coefficients with a productivity method. The analysis results show that the labor and material coefficients approach the AHSP based on the Minister of PUPR Regulation No. 8 of 2023, which is: workers (1:1.03), craftsmen (1:1.73), foremen (1:1.07), lightweight bricks (1:0.95), mortar (1:1.01), and HSPK (1:1.04). The analysis of the unit cost of masonry using 10 cm thick lightweight bricks with ready-mix mortar is lower compared to the unit cost of masonry using hollow bricks with a thickness of half a brick mixed at 1PC : 4 PS based on SNI DT 91-0009-2007, resulting in a comparison of 1 : 1.21, with a total difference obtained from the IPIT project at RSUD dr. R. Koesma Tuban amounting to Rp123,254,569.84 or 17.66% of the total masonry budget. It can be concluded that the coefficients in the unit cost guidelines for lightweight brick masonry in accordance with the Minister of PUPR Regulation No. 8 of 2023 can be implemented in construction projects, which is consistent with the removal of the unit cost guidelines for hollow brick masonry from the unit cost guidelines in Minister of PUPR Regulation No. 8 of 2023.

Keywords


AHSP, lightweight brick, coefficient, HSPK.

Full Text:

PDF

References


Abubakar, Y., Shirly Wunas, Wihardy Tjaronge, & Rudy Djamaluddin. (2017). Model Koefisien Produktivitas Pekerjaan Pemasangan Bata Ringan Pada Perumahan Sederhana. Prosiding Semnastek. Seminar Nasional Sains dan Teknologi, Jakarta.

Afrian, F., Mas’ud, F., & Arsyad, L. O. M. N. (2024). Produktivitas Pekerja Konstruksi pada Pekerjaan Dinding Bata Ringan Berdasarkan PUPR No. 1 Tahun 2022: (Studi Kasus: Pembangunan Rumah Susun STAIN Kendari Kampus II). MEDIA KONSTRUKSI, 9(2), 131–140. https://doi.org/10.33772/medkons.v9i2.17

Alami, N. (2021). Studi Komparasi Perbandingan Rencana Anggaran Biaya Antara Metode Analisa Harga Satuan Pekerjaan (AHSP) dan Standar Nasional Indonesia (SNI). Surya Beton: Jurnal Ilmu Teknik Sipil, Vol 5. No 1.

Anam, C., & Sugiyanto, S. (2022). Analisa Efisiensi Penggunaan Bata Merah Dibanding Bata Ringan Pada Proyek Pembangunan Gedung Madrasah Tsanawiyah Salafiyah Kerek Tuban. Rang Teknik Journal, 5(2), 235–247. https://doi.org/10.31869/rtj.v5i2.3119

Ayu Istri Lestari, I. G. A., Angga Diputera, I. G., Kurniari, K., & Wahyu Prasetya, I. W. (2022). Analisis Perbandingan Metode Pelaksanaan pada Pekerjaan Pasangan Dinding Batako dan Bata Ringan. Jurnal Ilmiah Kurva Teknik, 11(1), 25–30. https://doi.org/10.36733/jikt.v11i1.3931

Eppendie, A., & Kushartomo, W. (2023). Analisis Efektifitas Penggunaan Bata Ringan Sebagai Pengganti Bata Merah Pada Konstruksi Gedung Bertingkat. JMTS: Jurnal Mitra Teknik Sipil, 595–600. https://doi.org/10.24912/jmts.v6i3.23033

Ervianto, W. I. (2004). Teori Aplikasi Manajemen Proyek Konstruksi. Penerbit Andi.

Ervianto, W. I. (2023). Manajemen Proyek Konstruksi. Penerbit Andi.

Haryono, M. I. Y. I., Solin, D. P., & Farichah, H. (2025). Perbandingan Stabilitas Dinding Penahan Tanah Tipe Bronjong dengan Tipe Kantilever di Kabupaten Probolinggo. Jurnal Talenta Sipil, 8(2), 914. https://doi.org/10.33087/talentasipil.v8i2.1011

Hermawan, F., Wahyu Sejati, Muhammad Zaki, & Ardilla Jefri Karista. (2022). Estimasi Perbandingan Pekerjaan Dinding Panel GRC dan Bata Ringan Untuk Partisi Ruangan. SAINTEKS, Vol 10. No 2. https://doi.org/10.35583/js.v10i2.161

Hidayat, Moch. D. N., Hepiyanto, R., & Dhana, R. R. (2025). Manajemen Waktu dan Biaya Proyek dengan Sistem Crash Menggunakan Microsoft Project pada Peningkatan Jalan Soko – Karangbinangun. Jurnal Talenta Sipil, 8(2), 947. https://doi.org/10.33087/talentasipil.v8i2.955

Husain, B. A., Jantje B. Mangare, & Pingkan A. K. Pratasis. (2022). Produktivitas Pasangan Dan Plesteran Dinding Bata Ringan Pada Kasus Pembangunan Mess Dan Prasarana DENMADAM XIII/MDK. TEKNO, Vol 20. No 1. https://doi.org/10.35793/jts.v20i81.42467

Kementerian PUPR. (2023). Peraturan Menteri PUPR Nomor: 8 Tahun 2023. Kementrian PUPR, 683, 1–18.

Kementrian Pekerjaan Umum dan Perumahan Rakyat. (2022). Peraturan Menteri PUPR No 1 tahun 2022 Tentang Pedoman Penyusunan Perkiraan Biaya Pekerjaan Konstruksi Bidang Pekerjaan Umum dan Perumahan Rakyat. Menteri Pekerjaan Umum dan Perumahan Rakyat Republik Indonesia.

Khasanah, F., & Sugeng Dwi Hartantyo. (2016). Analisa Biaya Bangunan Pekerjaan Konstruksi Baja Menggunakan Metode HSPK dan SNI. Civilla: Jurnal Teknik Sipil Universitas Islam Lamongan, Vol 1. No 2.

Mashudin, M., & Hepiyanto, R. (2017). Perbandingan Biaya dan Waktu Pekerjaan Dinding Pasangan Bata Merah dan Batu Kumbung Perumahan Griya Permata Insani. Jurnal CIVILA, 2(2), 6. https://doi.org/10.30736/cvl.v2i2.77

Musyafa, A. & Iqbal Adie Surya Firdaus. (2023). Perbandingan Estimasi Biaya Pekerjaan Dinding Bata Merah, Bata Ringan, Batako dan M Panel. AJIE, 1–4. https://doi.org/10.20885/ajie.vol7.iss1.art1

Pambudi, A. K. A., & Rasio Hepiyanto. (2019). Perbandingan Biaya Pelaksanaan Pekerjaan Dinding Menggunakan Bata Ringan dan Bata Merah pada Perumahan Type 36. Civilla: Jurnal Teknik Sipil Universitas Islam Lamongan, Vol 4. No 1.

Prapto, P., & Haryadi, B. (2017). Studi Perbandingan Biaya Per 1 M2 Pekerjaan Pasangan Dinding Bata Ringan Dengan Pasangan Bata Merah. INERSIA lnformasi dan Ekspose Hasil Riset Teknik Sipil dan Arsitektur, 13(1). https://doi.org/10.21831/inersia.v13i1.14596

Rani, H. A. (2016). Manajemen Proyek Konstruksi. 99.

Rochim, M. N., Rahayu Isnin Astuti, Risma Dwi Atmajayani, & Yuniar Alam. (2022). Analisis Perbandingan Biaya dan Waktu Pemasangan Dinding Batu Bata Merah dan Batako Pada Pembangunan Gedung Kantor Urusan Agama (KUA) di Kecamatan Wates Kabupaten Blitar Jawa Timur. Jurnal Pendidikan: Riset dan Konseptual, Vol 6. No 1. https://doi.org/10.28926/riset_konseptual.v6i1.483

Rori, G., Deane RO Walangitan, & Revo L. Inkiriwang. (2020). Analisis Perbandingan Biaya Material Pekerjaan Pasangan Dinding Bata Merah Dengan Bata Ringan. Jurnal Sipil Statik, Vol 8. No 3.

Samsu. (2017). Metode Penelitian: (Teori Dan Aplikasi Penelitian Kualitatif, Kuantitatif, Mixed Methods, Serta Research & Development). Pusat Studi Agama dan Kemasyarakatan.

Surachman, M. A., & Prima Eko Agustyawan. (2019). Analisa Produktivitas Tenaga Kerja Harian dan Borongan pada Proyek RSUD Dr. Soegiri Lamongan. Vol 4. No 1. https://doi.org/10.30736/cvl.v4i1.312

Tahan, T. (2021). Perbandingan Rencana Anggaran Biaya Antara Metode SNI 2010 dan Analisis Harga Satuan Pekerjaan. Jurnal Kacapuri: Jurnal Keilmuan Teknik Sipil, 4(2), 379. https://doi.org/10.31602/jk.v4i2.6443

Widiantoro, O. (2017). Rencana Anggaran Biaya (Contruction Cost Estimate) (Buku Ajar). 1–81.

Widiasanti, I., & Lenggogeni. (2013). Manajemen Konstruksi. Dalam Widiasanti, Lenggogeni dan Irika.




DOI: http://dx.doi.org/10.33087/talentasipil.v9i1.1111

Refbacks

  • There are currently no refbacks.


Creative Commons License
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

Jurnal Talenta Sipil, Faculty of Engineering, Batanghari University
Adress: Fakultas Teknik, Jl.Slamet Ryadi, Broni-Jambi, Kec.Telanaipura, Kodepos: 36122, email: talentasipil.unbari@gmail.com


Creative Commons License This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.