Optimalisasi Waktu Proyek Pembangunan Rumah Susun dengan Metode PDM dan PERT

Efrat Ananta, Gunaedy Utomo, Reno Pratiwi

Abstract


The construction of the Polda Kaltim apartment building requires systematic time control because the project experienced a delay from the initial contract duration of 240 calendar days. The delay was mainly caused by material distribution constraints, limited workforce availability, and the lack of optimal periodic evaluation between the planned schedule and field realization. This study aims to analyze the critical path and the probability of achieving the evaluated project duration target of 270 calendar days using the Precedence Diagram Method (PDM) and Program Evaluation and Review Technique (PERT). The research data were obtained through literature review, observation, interviews, project documents, and duration-estimation questionnaires completed by 30 respondents. The PDM method was used to identify activity dependencies and critical paths, while the PERT method was applied to calculate expected time, standard deviation, variance, and project completion probability. The results show that the expected project duration is 267 days with a standard deviation of 3.51 days. The evaluated target duration of 270 days has an achievement probability of 80%. In addition, 59 critical activities were used in the PERT variance calculation and require intensive monitoring. Therefore, the integration of PDM and PERT can be used as a scheduling tool to evaluate target-duration achievement, identify critical activities, and formulate more measurable project time-control strategies.

Keywords


Project management; PDM; PERT; critical path; project completion probability.

Full Text:

PDF

References


Amani, W., Helmi, & Irawan, B. (2012). Perbandingan aplikasi CPM, PDM, dan teknik bar chart-kurva S pada optimalisasi penjadwalan proyek. BIMASTER: Buletin Ilmiah Matematika, Statistika dan Terapannya, 1(1), 15–22.

Alim, P. C. R., Pratiwi, R., & Devi, S. M. (2026). Analisis keterlambatan proyek pembangunan gudang dengan Precedence Diagram Method (PDM) dan Program Evaluation and Review Technique (PERT). Jurnal Talenta Sipil, 9(1), 116–130. https://doi.org/10.33087/talentasipil.v9i1.1110

Ardana, P. D. H., & Sudiarsana, I. W. (2023). Analisis penjadwalan ulang menggunakan metode Precedence Diagram Method pada proyek pembangunan ruang kelas baru di Madrasah Tsanawiyah Negeri (MTsN) Karangasem. Jurnal Ilmiah MITSU, 11(2), 51–62. https://doi.org/10.24929/ft.v11i2.2301

Elviyanti, Zulikasio, I. A., & Lalan, H. (2023). Analisa schedule dengan Precedence Diagram Method (PDM) proyek gedung oleh PT. X. Journal of Scientech Research and Development, 5(1), 449–458. https://doi.org/10.56670/jsrd.v5i1.152

Fazis, M., & Tugiah, T. (2022). Perencanaan proyek dan penjadwalan proyek. Jurnal Sosial Teknologi, 2(12), 1365–1377. https://doi.org/10.59188/jurnalsostech.v2i12.517

Febriana, W., & Aziz, U. A. (2021). Analisis penjadwalan proyek dengan metode PERT menggunakan Microsoft Project 2016. Surya Beton: Jurnal Ilmu Teknik Sipil, 5(1), 37–45. https://doi.org/10.37729/suryabeton.v5i1.1107

Hutomo, I. S., & Rohman, M. A. (2021). Penjadwalan probabilistik pada proyek Jalur Lintas Selatan LOT. 6. Jurnal Teknik ITS, 10(2), D217–D222. https://doi.org/10.12962/j23373539.v10i2.74300

Lase, D. W., & Nusa, A. B. (2024). Analisis penjadwalan proyek dengan metode PDM dan PERT pada pembangunan Gedung Sekolah Minggu HKBP Aek Kanopan Kecamatan Kualuh Hulu Kabupaten Labuhan Batu Utara. Jurnal Teknik Sipil, 3(1), 55–61. https://doi.org/10.30743/jtsip.v3i1.9553

Nanda, M. P., Kurniawati, M., & Riswanto, S. (2023). Penggunaan metode Project Evaluation Review Technique (PERT) dalam evaluasi perencanaan penjadwalan proyek. Jurnal Teknik Sipil, 17(3), 163–173. https://doi.org/10.24002/jts.v17i3.7181

Pandya, M. W. Y., Nasution, D. S. D., Hendriyanti, I., & Pratiwi, R. (2024). Analisis resource leveling menggunakan Precedence Diagram Method (PDM) pada Gedung Mako Lanal Balikpapan. Jurnal Talenta Sipil, 7(2), 445–454. https://doi.org/10.33087/talentasipil.v7i2.488

Pangestika, E. A., Syahrudin, & Rafie. (2022). Analisis biaya dan waktu pada proyek pembangunan Gedung Kuliah Terpadu Politeknik Negeri Pontianak dengan metode PDM dan PERT. JeLAST: Jurnal Teknik Kelautan, PWK, Sipil, dan Tambang, 9(1). https://doi.org/10.26418/jelast.v9i1.53760

Purwanto, A. Y., Utomo, G., & Pratiwi, R. (2026). Penerapan metode PDM dan PERT pada proyek pembangunan Pusat Layanan Haji dan Umroh Terpadu Kota Balikpapan. Jurnal Talenta Sipil, 9(1). https://doi.org/10.33087/talentasipil.v9i1.873

Rahma, K. A., & Kamandang, Z. R. (2023). Analisis penjadwalan proyek gedung bertingkat menggunakan metode CPM dan PERT: Studi kasus proyek pembangunan tahap 1 Rumah Sakit Muhammadiyah Gresik. Jurnal Ilmiah Universitas Batanghari Jambi, 23(2), 1275–1279. https://doi.org/10.33087/jiubj.v23i2.4126

Setiawan, D. C., Ridwan, A., & Suwarno. (2021). Optimalisasi penjadwalan proyek pembangunan Gedung Puskesmas Badas menggunakan Critical Path Method–Project Evaluation and Review Technique (CPM-PERT). Jurnal Manajemen Teknologi dan Teknik Sipil, 4(2), 71. https://doi.org/10.30737/jurmateks.v4i2.2011

Wicaksono, M. H., Sugandi, R. M., & Alfianto, I. (2024). Pengendalian durasi optimal pada pembangunan Myze Hotel Sumenep menggunakan CPM dan metode PERT. BENTANG: Jurnal Teoritis dan Terapan Bidang Rekayasa Sipil, 12(1), 49–62. https://doi.org/10.33558/bentang.v12i1.7323




DOI: http://dx.doi.org/10.33087/talentasipil.v9i2.1342

Refbacks

  • There are currently no refbacks.


Creative Commons License
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

Jurnal Talenta Sipil, Faculty of Engineering, Batanghari University
Adress: Fakultas Teknik, Jl.Slamet Ryadi, Broni-Jambi, Kec.Telanaipura, Kodepos: 36122, email: talentasipil.unbari@gmail.com


Creative Commons License This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.