Penjadwalan Ulang Proyek Peningkatan Jalan Bulu – Jatirogo (Lanjutan) Kabupaten Tuban dengan Menggunakan Metode LSM (Linear Scheduling Method)

Evi Kumalasari, Sugeng Dwi Hartantiyo, Yosef Cahyo

Abstract


One of the main indicators of project success is the completion of work according to schedule. Inaccuracy in scheduling can result in delays or cost overruns. Therefore, scheduling is a crucial element in the sequence of project implementation. This study aims to calculate the project duration using the LSM method and to determine which is more effective between scheduling with the LSM (Linear Scheduling Method) and the existing method. The research employs a quantitative approach focusing on the collection and analysis of measurable and countable variables to obtain objective results, and applies a mathematical approach. Microsoft Excel software was utilized as a tool to recalculate the project execution duration and to develop linear charts based on groups of activities with linear characteristics. The analysis results show that for the Bulu–Jatirogo Road Improvement Project (continuation) in Tuban Regency, the use of the Linear Scheduling method can shorten the project duration to 50 days, which is significantly more efficient compared to the previous method that required 110 days. This 60-day difference indicates that the Linear Scheduling method is superior in the effectiveness of schedule planning.

Keywords


Linear Scheduling Method; Project Scheduling; Duration Efficiency.

Full Text:

PDF

References


Belferik, R., Ardiyan, A., Zulkarnain, I., Munizu, M., Samosir, J., Afriyadi, H., & Prasetyo, A. (2023). Manajemen Proyek. Jambi: PT. Sonpedia Publishing Indonesia.

Callahan, M. (1992). Construction Project Schedulling . McCraw Hill, Inc.

Chrzanowski, E., & Johnston, D. (1986). Application of Linear Scheduling. Journal of Construction Engineering and Management.

Fatimah, S., Hepiyanto, R., & Dhana, R. R. (2025). Analisis Biaya dan Waktu pada Proyek Pembangunan Gudang dan Musholla Area Mainsub Tuban III-IV dengan Metode Earned Value. Jurnal Talenta Sipil, 837-847.

Harmelink, D., & Rowings, J. (1998). Linear Scheduling Model: Development of Controlling Activity Path. Journal of Construction Engineering and Management, 263-268.

Jazuli, M., & Dhana, R. (2024). Analisis Biaya dan Waktu pada Proyek Jembatan (Studi Kasus Proyek Pembangunan Jembatan Candisari Sambeng Kabupaten Lamongan) dengan Menggunakan Metode Earned Value. Jurnal Talenta Sipil, 73-82.

PMI. (2021). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) - Seventh Edition and the Standard for Project Management (ENGLISH). Project Management Institute.

Rahayu, N., & Mawardi, E. (2024). Analisa Penjadwalan Proyek Kontruksi Menggunakan. Jurnal Ilmiah Mahasiswa Teknik Sipil UTU (JITSU), 49-55.

Ralahallo, F., Jaya, F., & Tukimun. (2024). Manajemen Proyek. Yogyakarta: Sulur Pustaka.

Santosa, B. (2009). Manajemen Proyek. Yogyakarta: Graha Ilmu.

Selinger, S. (1980). Construction Planning for Linear Projects. Journal of The Construction Division , 195-205.

Shi, J. (2002). Current Teaching of Linear Scheduling Method .

Soeharto, I. (1995). Manajemen proyek dari Konseptual sampai Operasional. Jakarta: Erlangga.

Verolio, & Pamadi, M. (2023). Analisa Penjadwalan Metode Linear Scheduling Method atau Line of Balance (LSM/LoB) Perumahan Deyely Residance Kota Batam . Civil Engineering and Architectur Journal, 1-10.

Voster., M., Beliveau, Y J, & Bafna, T. (1992). Linear Schaduling and Visualization. Transportation Research Board.




DOI: http://dx.doi.org/10.33087/talentasipil.v9i1.1066

Refbacks

  • There are currently no refbacks.


Creative Commons License
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

Jurnal Talenta Sipil, Faculty of Engineering, Batanghari University
Adress: Fakultas Teknik, Jl.Slamet Ryadi, Broni-Jambi, Kec.Telanaipura, Kodepos: 36122, email: talentasipil.unbari@gmail.com


Creative Commons License This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.